Course outline
- Formation pressure
- Normal / Abnormal pressure
- Hydrostatic effects with different density mud
- Primary well control
- Leak off test, maximum allowable surface pressure
- Pump pressure and its relationship with discharge/mud density
- Equivalent circulating density
- Causes of reduced hydrostatic head
- Early warning signs
- Positive kick signs while drilling & tripping
- Trip margin
- Swab and surge effects and associated calculations
- Shut in procedures
- Observation & interpretation of shut in pressure
- SIDPP, SICCP, Pit gain
- SIDPP with NRV in string
- Shut in pressures in horizontal wells
- ICP, FCP, KMW
- Choke line friction
- Effect of ROP & permeability on SICP
- Hydrocarbon kick behavior in oils based mud
- Closed and open well migration of gas
- Pre kick and kill sheet data
- Calculation of influx gradient
- Classroom exercises, distribution of assignment booklet
- Simulator
- Line up procedure before drilling
- Recording slow circulation rate
- Recognition of drill brake and corrective measure to be taken
- Discussion on assignment
- Kick handling methods
- Step by step procedure for driller and Wait & Weight method
- Effect on BHP when surface pressure are not maintained as per schedule during killing
- Concurrent method
- Volumetric method
- Riser margin and subsea stack gas removal
- Well control in deviated wells
- Associated calculations
- Ram type preventer
- Closing ratio & opening ratio
- Annular preventer Rings & Flanges
- Stripping operation
- Inside BOP’s
- Hang off procedure
- Diverter system
- Test plug & cup tester
- Testing of BOP stack
- Function test
- Pressure test
- Simulator training
- Petection of kick
- Well shut in
- Recording of shut in pressure
- Bringing the pump to kill rate
- Well killing by Driller’s method
- Discussion on assignments
- BOP control unit
- Usable fluid calculation
- Sizing of accumulator (surface & subsea)
- BOP operation from Driller’s/Tool Pusher panel
- Trouble shooting of accumulator and surface equipment
- Choke and kill manifold
- Trip tank
- Flow indicator
- Mud gas separator
- Vacuum degasser
- Unusual situations in well control
- Plugged and washed bit nozzle / choke string washout
- Lost circulation
- Total & partial pump failure
- Kick handling when surface pressure approaches MAASP
- Bull heading
- Hydrate formation and removal
- Simulator training
- Well killing by Weight & Wait method
- Unusual situation during well killing
- Gas migration
- Discussion on assignment & class room exercises on well control principal and procedure
- Mock test on IWCF pattern
- Post-test discussion
- Simulator test for batch no. 1,2,3 & 4 and video films on well control related topics
- Simulator test for batch no 5,6,7, & 8 and video films on well control related topics
- Discussions on assignments
- Classroom exercise on BOP equipment & control unit
- IWCF equipment test
- IWCF test principal & procedure test (Drillers 1 ½ hrs & Supervisor 2½ hrs